A&A works in Singapore are changes to an existing building, such as new floor space, new openings, a roof garden or a change of use. You need them when a building no longer fits the way you work. Most A&A works need approval from one or more of URA, BCA and SCDF, plus JTC consent on JTC land, before work starts.
However, not every change needs a full submission. Some internal works need no planning permission. Also, some minor fire safety changes use a short lodgement route. This guide explains when owners need A&A works, which approvals apply, and how the process runs from brief to handover.
Key Takeaways
A&A stands for additions and alterations. It covers any change to a building that already exists, rather than a new one. Typical examples include:
A&A differs from a simple fit-out. A fit-out mostly adds finishes, partitions and services inside a space. By contrast, A&A works often touch the structure, the fire safety design or the approved floor area. So they usually need a Qualified Person (QP) to plan and submit them. A QP is a registered architect or engineer.
Owners tend to start A&A works for one of four reasons. First, the business grows and needs more floor space or higher loads. Second, a new tenant or process needs a different layout or use. Third, an older building needs work to meet current rules. Finally, owners add amenities, such as a roof garden or a staff area.
Each reason leads to a different set of approvals. For example, a change of use brings in SCDF and URA. In contrast, a strengthening job is mainly a BCA structural matter. So it pays to define the scope clearly before your QP starts.
URA exempts some works from planning permission. These include internal re-partitioning within tenanted areas if the use, quantum and floor area stay the same. Also exempt are light partitions in non-residential buildings, air-con works and like-for-like finishes. However, works that change floor area or use need approval. Also, these exemptions do not cover conservation buildings, national monuments or some planning areas.
On JTC or HDB land, factory and warehouse A&A can use URA’s plan lodgment route, which costs $850 for additions and alterations. Before that, JTC states lessees must obtain its plan consent for A&A works.
BCA states that a permit is required for all building works except insignificant ones, as listed in the First Schedule of the Building Control Regulations. Only a QP who is a civil or structural professional engineer may apply for structural plan approval.
Also, if A&A work materially affects key structural parts, such as strengthening works, BCA needs an Accredited Checker certificate. Then the permit to start structural works is a joint application by the owner, the QP and the builder.
Some small items need no plan at all. For instance, BCA’s list for other types of buildings includes a single-storey booth or guardhouse up to 10 square metres. It also covers a light awning that sticks out no more than 3 metres, if the space below stays open.
SCDF states that anyone planning fire safety works must first get plan approval. Some minor works may be exempt or need only a Minor Alterations or Additions lodgement. For those, the QP lodges plans through CORENET at $90 per submission before work starts.
A change of use also needs SCDF’s prior approval. SCDF has warned that breaches can lead to fines of up to $10,000, and up to $200,000 for serious offences, as well as jail terms.
Under a URA and BCA circular of 23 July 2026, major A&A with an affected or replaced GFA of 5,000 square metres or more must use CORENET X from 1 October 2026. Additions that create 5,000 square metres or more of new GFA are also in scope.
The table gives a first view only. Your QP must confirm the exact route, since it depends on scope, use and location.
| Type of work | URA | BCA | SCDF |
|---|---|---|---|
| Lightweight internal partitions, same use | Exempt if use, quantum and floor area stay the same | Check against the insignificant works list | Check if exits or fire systems change |
| New mezzanine or extra floor area | Approval needed, as GFA changes | Structural plans and permit | Plan approval |
| Strengthening beams or slabs | Usually not affected | Structural plans, Accredited Checker certificate and permit | Check if fire protection is affected |
| Change of use | Approval needed | Check loads and structure | Prior approval needed |
| Roof garden or rooftop structure | Check external works and GFA | Structural plans for added loads | Check roof access and exits |
Works in buildings that stay in use need extra care. So your builder should plan phasing, hoarding and safe routes for staff and visitors. For the wider approval picture on industrial sites, see our guide to warehouse costs, timelines and approvals.
Weima Builders lists A&A works among its core services, next to structural, architectural and fit-out works. We hold BCA CW01 grade A1 and a General Builder Class 1 licence.
For example, we carried out A&A works and a roof garden at Level 4 of Micron, 990 Bendemeer Road, completed in 2020. You can read more about our A&A and construction services.
Planning A&A works on an industrial or commercial building? Contact Weima Builders early, so we can review buildability, phasing and the permit plan with your QP team. Call +65 6548 3000 or email info@weima.sg.
Related service: see our BCA A1 main contractor services.
No. BCA requires a permit for all building works except insignificant ones listed in the First Schedule of the Building Control Regulations. Examples include a single-storey booth up to 10 square metres. However, works that affect the structure, such as new openings or strengthening, need structural plan approval by a professional engineer and a permit before they start.
Often not. URA exempts internal re-partitioning within tenanted areas if the use, quantum and floor area stay the same and common areas are not affected. Lightweight partitions in non-residential buildings are also exempt. However, works that add floor area or change the use need approval, and exemptions do not apply to conservation buildings.
It is a shorter route for minor fire safety changes listed in the Schedule to the fire safety regulations. A Qualified Person lodges the plans through CORENET before work starts, at $90 per submission. The QP certifies whether the works affect the existing fire protection systems. Works outside that Schedule need full SCDF plan approval instead.
BCA requires an Accredited Checker certificate when additions and alterations materially affect key structural elements, such as strengthening works. It is one of several cases BCA lists for this certificate. So ask your structural engineer early whether your scope triggers it, and allow for the extra step in your programme.
Yes, for large schemes. From 1 October 2026, major A&A works with an affected or replaced gross floor area of 5,000 square metres or more must use CORENET X. Additions that create at least 5,000 square metres of new floor area are also included. Smaller A&A projects may continue to use CORENET 2 for now.
Sources:
1 Tai Seng Avenue Tower A #06-09 Tai Seng Exchange Singapore 536464
Monday to Friday
8.30am to 6pm
info@weima.sg
+65 6548 3000
“For every project we complete, we think about the fact that the work we do is something you live with every single day.”