Factory construction in Singapore’s Tuas area starts with the right land and zoning. Then it moves through NEA siting advice, JTC consent, building approvals and a MOM factory filing before the plant starts running. Tuas sits next to Singapore’s new container port. Also, recent state land sales there offer industrial sites on fixed leases.
This guide is for owners planning a new plant in Tuas. It covers why the location matters and how to check that your process fits the site. It also covers which approvals apply to a factory, and what to plan for in design and build.
Key Takeaways
Tuas sits at the western end of Singapore, next to the country’s new container port. According to the Ministry of Transport, Tuas Port officially opened in September 2022. Once it is fully built in the 2040s, it will be able to handle 65 million TEUs a year. It will also bring all of Singapore’s container port work to one place.
Also, logistics support is growing around it. For example, at the groundbreaking of PSA’s Supply Chain Hub @ Tuas in October 2024, Prime Minister Lawrence Wong said the hub will handle part-load cargo, cold storage and special goods such as chemicals. He also noted that Keppel Distripark will close by 2027.
So for manufacturers that import inputs or export by sea, Tuas can cut haulage distance to the port.
There are three usual routes to a factory site in Tuas:
The latest IGLS supply is all in Tuas. The Ministry of Trade and Industry’s 2H 2026 IGLS release, dated 29 June 2026, lists four Confirmed List sites totalling 6.75 hectares. They are at Tuas Road, Tuas West Drive, Tuas View Lane and Tuas Avenue 20, with tenures of 23 or 36 years. For example, the Tuas Road site has Business 2 zoning and a plot ratio of 1.4.
Next, check the zoning rules. URA states that general and special industries go in Business 2 zones. In addition, URA’s use quantum rules require at least 60 per cent of B2 industrial GFA to stay in industrial use. So offices, canteens and other support space share the last 40 per cent.
Finally, your lease term shapes the brief. A short lease may favour a simple, quick build. In contrast, a long one may justify a more flexible frame.
Factories differ from warehouses because of what goes on inside. Fumes, noise, hazardous goods and waste water all affect where a plant may sit.
First, NEA puts industries into four classes: Clean, Light, General or Special. It then keeps buffer distances between industry and homes or care homes. According to URA’s Business 2 notes, NEA requires a 100 metre nuisance buffer from a B2 zone to the surrounding area. The detailed rules sit in NEA’s Code of Practice for Pollution Control, SS 593.
Next, if you are unsure, use NEA’s Industrial Siting Consultation. You may apply for a new industrial building, or for a new process at an existing site. NEA aims to reply within 7 working days of complete information. However, it may take longer if NEA must ask other agencies or survey the site.
So prepare a process flowchart and a list of raw materials and pollution control kit before you apply. Then the same details help your design team size services and plant rooms.
A factory needs the same core building approvals as any industrial project. It also needs some that relate to how it runs. The table sets out the main ones.
| Agency | What it covers | When |
|---|---|---|
| NEA | Industrial Siting Consultation for the process and site | Early, before the design is fixed |
| JTC | Plan consent as landowner for new erection or A&A | Before works start |
| URA | Plan lodgment for factories on JTC or HDB land, with JTC or HDB endorsement | At design stage |
| BCA | Structural plans and permit to start works | Before construction |
| SCDF | Fire safety plan approval and Fire Safety Certificate | Design stage and before occupation |
| MOM | Factory notification or registration | Before operations start |
However, the MOM step is easy to miss. MOM states that factories must notify or register their activities before starting operations. Higher-risk sites need a Certificate of Registration. Examples include wafer fabs, drug plants and metal works with more than 100 staff. In contrast, lower-risk factories file a one-time notice.
For more on plan lodgment fees, CORENET X thresholds and TOP timing, see our guide to industrial construction costs, timelines and approvals.
Factory design starts with the process, not the shell. So bring your process engineers and your builder into the brief early. Here are the points that tend to drive structure and cost:
Some owners combine production and storage over several floors. If trucks must reach upper floors, read our comparison of ramp-up and conventional warehouse designs before you fix the layout.
Weima Builders is a BCA CW01 grade A1 general builder with a General Builder Class 1 licence. We work on structural, civil engineering, foundation and M&E works as well as building works.
In Tuas, we carried out the RC works at 5 Tuas Avenue 5 for a new seven-storey single-user ramp-up factory and warehouse with an ancillary office, completed in 2019. See our construction services for design and build and project management.
Planning a new factory in Tuas or elsewhere in the west? Contact Weima Builders to review your brief, site and structure before you commit to a design. Call +65 6548 3000 or email info@weima.sg.
Related service: see our warehouse construction services in Singapore.
Most heavier factories need Business 2 zoning, because URA places general and special industries in Business 2 zones. At least 60 per cent of the industrial GFA must stay in industrial use, with ancillary uses such as offices capped at 40 per cent. Check the exact site zoning and conditions in the land sale or JTC documents.
It is NEA’s check on whether an industrial activity suits a site, so that it does not cause nuisance to residents. You can apply for a new industrial building or a new process at an existing site. NEA aims to reply within 7 working days of full details. However, a site survey or input from other agencies can add time.
MOM requires factories to either notify or register their activities before operations start. Higher-risk sites need a Certificate of Registration. Examples include drug plants, wafer fabs and metal works with more than 100 staff. Lower-risk factories submit a one-time notification. Some very small, low-risk workplaces need neither.
Lease terms vary by site. For example, the four sites on MTI’s 2H 2026 Industrial Government Land Sales Confirmed List are all in Tuas and carry tenures of 23 or 36 years. Since your tenure affects payback and design life, confirm it before you set the building brief and budget.
Tuas sits next to Tuas Port, which officially opened in September 2022. When fully completed in the 2040s, the port will be able to handle 65 million TEUs a year. For manufacturers that ship by sea, this can cut haulage time. Recent state land sales have also offered industrial sites in Tuas.
Sources:
1 Tai Seng Avenue Tower A #06-09 Tai Seng Exchange Singapore 536464
Monday to Friday
8.30am to 6pm
info@weima.sg
+65 6548 3000
“For every project we complete, we think about the fact that the work we do is something you live with every single day.”