For an industrial fit-out, Singapore owners should follow six steps: set the operations brief, check the building, design and get approvals, appoint a builder, carry out the works, then test and hand over. The fit-out turns an empty warehouse or factory space into a working site. So it covers racking, mezzanines, offices, power, fire safety and process services. Most delays come from late approvals, or from a brief that changes after design starts.
This guide is for warehouse and factory owners and tenants. It walks through each step and the agency rules that apply. Also, it focuses on industrial space, not offices.
Key Takeaways
A fit-out prepares a bare shell for a set use. For a warehouse, that may mean racking, a mezzanine office, dock gear and lights. For a factory, it may also add process power, compressed air, exhaust, clean areas and heavy plant bases.
The table below lists common fit-out items and the checks that usually come with them. However, your QP will confirm the exact approvals for your site.
| Fit-out item | Check or approval to plan for |
|---|---|
| Mezzanine floor or new openings | Structural check by an engineer, or an Accredited Checker if key parts of the frame are affected |
| Racking, partitions and new rooms | Fire safety review by a QP, and SCDF plan approval where fire safety works are involved |
| Power upgrade or new switchboard | EMA licence if above 45 kVA, through a Licensed Electrical Worker |
| Any works on JTC land | JTC consent and other agency approvals before works start |
| Start of factory work | MOM factory notice or registration |
So the fit-out is more than a build job. Because design, approvals and checks form a chain, they must line up with your move-in date.
First, describe how the space will work. Your brief drives every later choice, so take time here. Cover these points:
Then fix the brief before design goes too far. If you add a mezzanine or double the racking height later, the structure, sprinklers and approvals may all change.
Next, check what the existing building can take. Ask your engineer and builder to review:
This step often decides the budget. For example, a slab that cannot take your racking may need strengthening, and that adds structural approvals.
Then your consultants turn the brief into drawings and plans for approval. The approvals depend on the works and the site.
JTC land. JTC’s fitting-out and renovation process states that all such works need JTC and relevant agency approval before they start. Your consultant applies for JTC’s consent first. Then the consultant submits to agencies such as URA, SCDF’s Fire Safety and Shelter Department and NEA.
Fire safety. SCDF requires plan approval for fire safety works. Those plans must be prepared and submitted by QPs who are registered architects or professional engineers.
Structure. If you add a mezzanine or cut new openings, check the structural route. BCA’s structural plan page says a professional engineer endorses A&A works that do not affect structural stability. However, works that materially affect key structural elements need an Accredited Checker’s certificate. Our guide to A&A works and approvals explains this in more detail.
Next, appoint a main contractor who can handle structural, architectural and M&E works together. Also check its BCA licence, safety record and past industrial jobs. Our guide to factory construction for industrial developers covers related checks.
Then plan the site rules. In multi-tenant buildings, the landlord or managing agent sets them. For example, JTC’s process says contractors request to start works through the managing agent’s permit system. They must submit a risk assessment, method statement, worker list and, where needed, work-at-height certificates. JTC puts that review at less than 20 days.
JTC’s site rules also limit noisy works to after working hours. In addition, weekend and public holiday works need prior approval. Common areas must be protected, with joint checks before and after the works. So build these limits into your programme from the start.
Finally, test every system and close out the approvals. A typical close-out list includes:
Also collect as-built drawings, test reports and warranties at handover, because your site team will need them for upkeep and future changes.
Weima Builders is a BCA CW01 A1 main contractor with a General Builder Class 1 licence. Our construction services include fit-out, A&A works, structural works, architectural works and M&E works. So one team can handle the whole build side of the job.
For example, we carried out fitting-out works for an end user on the 5th storey of a warehouse at 24 Penjuru Road, completed in 2019. On fit-out jobs, we check loads, services and landlord rules before we price the works, so there are fewer surprises later.
Planning an industrial fit-out? Singapore warehouse and factory owners can send us your floor plans, racking layout and target move-in date. Then we will help you plan the works, approvals and handover. Contact Weima Builders, call +65 6548 3000 or email info@weima.sg.
Related service: see our A&A contractor services in Singapore.
Yes. JTC states that all fitting-out and renovation works need JTC and relevant agency approval before they start. Your consultant, such as a professional engineer, registered architect or QP, applies for JTC’s consent. Then the consultant submits to agencies such as URA, SCDF and NEA, and advises which approvals your works need.
A Qualified Person does. SCDF states that plans for fire safety works must be prepared and submitted by QPs who are registered architects or professional engineers. After the works, the owner must obtain a Fire Safety Certificate before using or occupying the premises. SCDF issues it only once all fire safety works are complete.
Usually, it needs a structural check. BCA lets a professional engineer sign off A&A works that do not affect the building’s stability. But if the works have a real effect on key parts of the frame, such as strengthening, you need an Accredited Checker’s sign-off. Your engineer will also check that the slab and columns can take the new loads.
If the premises count as a factory under the WSH Act, yes. MOM states that all factories must notify or register before they start work. Factories with high-risk work apply for a Certificate of Registration, while low-risk ones send a one-time notice. Some very low-risk sites with fewer than 10 staff are exempt.
EMA says a licence is needed for non-domestic power set-ups with an approved load above 45 kVA. Set-ups used in hazardous trades need one at any load. Your Licensed Electrical Worker, or LEW, checks the set-up on site. So if your fit-out raises the power load, plan the licence early in the job.
Sources:
1 Tai Seng Avenue Tower A #06-09 Tai Seng Exchange Singapore 536464
Monday to Friday
8.30am to 6pm
info@weima.sg
+65 6548 3000
“For every project we complete, we think about the fact that the work we do is something you live with every single day.”