A main contractor in Singapore signs the building contract with you, runs the site and answers for the whole job. A nominated subcontractor is a specialist that you or your consultant choose, but who then works under the main contractor. So the real difference is simple. It comes down to who picks the firm, who signs with it and who pays when things go wrong.
Getting this split right early saves disputes later. This guide explains each role, compares the common contract set-ups and lists the clauses owners should check before tender.
Key Takeaways
First, the main contractor is your single point of contact for building works. Then it prices the job, plans the programme, hires the trades and hands over the finished building.
BCA states that generally only main contractors apply for a General Builder licence. This applies to building works where plans need approval. Subcontractors usually do not need one, except for specialist works such as piling or structural steelwork. Also, a Class 1 licence covers projects of any value, while Class 2 covers projects of $6 million or less.
Registration is a separate check. BCA states that all firms that hire construction S Pass or Work Permit holders must register with CRS. That rule covers main contractors and subcontractors alike.
The main contractor directs most of the workers on site. So it carries heavy duties under the Workplace Safety and Health Act. MOM states that an employer must run risk assessments and give proper training and supervision. Also, MOM defines the occupier as the person who has control of the premises.
But owners have duties too. As a principal, you must make sure the firm you engage is able to do the work. If you tell the contractor’s workers how to do the job, MOM says you take on employer duties as well.
A nominated subcontractor is a specialist that the owner or the owner’s consultant selects. However, the main contractor then signs the subcontract and manages that firm on site. Owners often nominate when they want a say in brand, design or price. Lifts, facades and special M&E systems are common examples.
Also, public sector projects use a standard form for this. BCA publishes the Standard Conditions for Nominated Sub-Contract alongside the PSSCOC, with a supplement updated in July 2017. Private projects often borrow similar ideas, but the exact terms vary. So always read the actual clauses rather than assume.
In practice, there are three common ways to bring a specialist onto a project. Each one shifts control and risk in a different direction.
| Set-up | Who picks the firm? | Who signs with it? | Who usually manages it on site? |
|---|---|---|---|
| Domestic subcontractor | Main contractor. | Main contractor. | Main contractor. |
| Nominated subcontractor | Owner or consultant. | Main contractor. | Main contractor. |
| Direct contractor | Owner. | Owner. | Owner, with site rules set by the main contractor. |
In short, the more the owner chooses, the more risk tends to come back to the owner. A domestic subcontract keeps it all with the main contractor. A direct contract keeps far more with you.
The answer depends on your contract. Still, a few points apply on most private jobs.
If a nominated firm runs late, the main contractor may claim an extension of time. Whether it gets one depends on the clauses. So agree upfront how you will treat delay by a nominated firm.
Next, think about design. If the owner’s consultant designed the nominated package, the main contractor may refuse to take design liability for it. Then you may need a direct warranty from the specialist.
Payment is clearer because the law sets a floor. For example, section 9 of the Building and Construction Industry Security of Payment Act says a pay when paid clause is unenforceable. It has no effect. So a main contractor cannot tie its payment to a subcontractor to the date the owner pays it. Also, BCA notes that the Act covers main contractors, subcontractors, consultants and suppliers, and offers adjudication for payment disputes.
Before you tender, ask your consultant to cover these points in writing.
For the last point, our guide on how to verify a BCA registered contractor walks through the official checks. Still choosing a contract route? Then compare design and build vs traditional procurement first. That choice shapes how nomination works.
Weima Builders is a BCA CW01 A1 contractor with a General Builder Class 1 licence. So we can act as the main contractor on projects of any value. Our scope covers structural, architectural, A&A and M&E works. We also offer design and build and project management.
For example, at 12 Penjuru Lane we delivered a 4-storey single-user warehouse in 2023. It has a mezzanine ancillary office and roof container parking. You can see our full list of main contractor services on our site.
Planning an industrial or commercial build and unsure how to split the packages? Talk to us before tender. Then we can walk through which works suit a main contract and which may suit nomination. Call +65 6548 3000, email info@weima.sg or send us your project details.
Related service: see our BCA A1 main contractor services.
A main contractor signs the building contract with the owner. It then plans the programme, manages subcontractors and runs the site. For building works that need plan approval, BCA states that generally only main contractors apply for a General Builder licence. It is your single point of contact from site possession to handover.
In most set-ups, the main contractor pays the nominated subcontractor, because the main contractor signs the subcontract. The owner then pays the main contractor. Under the Security of Payment Act, a pay when paid clause has no effect. So the main contractor cannot wait for the owner’s payment before paying its subcontractor.
It depends on the contract. The main contractor usually manages the work on site. But it may refuse design liability if the owner’s consultant designed the package. So state who carries design and workmanship risk for each package. Also ask key specialists for direct warranties.
BCA states that subcontractors usually do not need a General Builder licence. However, firms that do specialist works need a specialist builder licence. Examples include piling, ground support, precast concrete and structural steelwork. Also, any firm that hires construction S Pass or Work Permit holders must register with CRS.
Yes. An owner can sign a direct contract with a specialist. However, the owner then takes on more of the coordination, delay and interface risk. The main contractor will still need site rules for that firm. So agree access, safety and programme terms with both parties before work starts.
Sources:
1 Tai Seng Avenue Tower A #06-09 Tai Seng Exchange Singapore 536464
Monday to Friday
8.30am to 6pm
info@weima.sg
+65 6548 3000
“For every project we complete, we think about the fact that the work we do is something you live with every single day.”